컨스텔레이션 에너지, 미국 쓰리마일 원전 재가동 위해 변압기 1400억원어치 주문
=>
마소 데이터센터에 2028년부터 20년간 공급하기 위해 가장 빨리 주문
= 리드타임이 가장 큰 병목 “변압기”라는 것
Constellation orders $100 million transformer for Three Mile Island restart
https://www.reuters.com/business/energy/constellation-orders-100-million-transformer-three-mile-island-restart-2024-10-16/
Constellation Energy (CEG.O)
, opens new tab
has ordered a main power transformer for the Three Mile Island nuclear reactor it is attempting to restart in Pennsylvania, pushing ahead with work critical to the plant's revival, Reuters learned on a tour of the site on Wednesday.
The transformer is expected to be the biggest single piece of equipment that will need to be replaced for restart of the plant. It will cost about $100 million, said Constellation, the owner of the plant, which is investing $1.6 billion to revive the operation over the next four years.
Separate Unit 1, which Constellation wants to resurrect, shut in 2019 for economic reasons. Constellation expects Unit 1 to begin producing power in 2028, but there is a series of physical hurdles, along with U.S. and local regulations, that must be completed first.
=>
마소 데이터센터에 2028년부터 20년간 공급하기 위해 가장 빨리 주문
= 리드타임이 가장 큰 병목 “변압기”라는 것
Constellation orders $100 million transformer for Three Mile Island restart
https://www.reuters.com/business/energy/constellation-orders-100-million-transformer-three-mile-island-restart-2024-10-16/
Constellation Energy (CEG.O)
, opens new tab
has ordered a main power transformer for the Three Mile Island nuclear reactor it is attempting to restart in Pennsylvania, pushing ahead with work critical to the plant's revival, Reuters learned on a tour of the site on Wednesday.
The transformer is expected to be the biggest single piece of equipment that will need to be replaced for restart of the plant. It will cost about $100 million, said Constellation, the owner of the plant, which is investing $1.6 billion to revive the operation over the next four years.
Separate Unit 1, which Constellation wants to resurrect, shut in 2019 for economic reasons. Constellation expects Unit 1 to begin producing power in 2028, but there is a series of physical hurdles, along with U.S. and local regulations, that must be completed first.